Call us: (905) 366 9700
Legal Blog
Arbitration
Carillion Construction Inc. v. Imara (Wynford Dr) Ltd. 2015 Ont SCJ
Owner wanted to invoke arbitration clause with general. Master refused for two main reasons. First, the owner had issued its own civil action against general and then waited 7 months to seek a stay to the general’s actions. During that time, multiple liens were registered, claims were issued, and a reference joined them into a single court proceedings. Therefore, the owner acted inconsistently with an election to arbitrate and waived arbitration under the contract. In any case, the owner unduly delayed its request for arbitration. Second, there were approximately 6 actions and 10 lien claims involving the general and the owner and another 50 lien claims involving subs of the general. The arbitration clauses were different in the prime contract than in the subcontracts and the owner did not want the subs to be involved in the arbitration with the general. This would be unfair to the general and would lead to multiple trials; for that reason also, the owner was estopped from insisting on arbitration.