Employment Professionals Canada Inc. v. Steel Design and Fabricators (SDF) Ltd. 2016 Ont SCJ

As in the Frank’s Drilling case, the court held that the limitation time for a breach of trust claim against a director did not start to run until (at least) when the corporate contractor breached its trust and the corporate contractor did not breach its trust until the owner paid it.