Legal Blog: Construction
Minefield
We often refer to construction lien law as construction litigation, but with security. The problem for practitioners who dabble in the area is that lien law is also a minefield waiting to blow up on unwary or inexperienced lawyers. Sometimes mistakes can be cured; often they cannot be. Fortunately, lawyers are insured and LawPro, the lawyers’ insurer, will appoint a construction lawyer who knows what to do to deal with these mistakes and sometimes turn a sow’s ear into a silk purse. One such case was Gay Company Limited v. 962332 Ontario Inc., a 2023 decision of the Superior Court of Justice.
What Happened
We are actually not entirely sure – because the references to plaintiff and defendant are interposed from what we would expect. However, we will assume that a contractor registered a lien against the lands of an owner for $767,000. But it is not quite that simple.
Continue Reading >Exclusion Clauses
What happens when a contractor buys material from a supplier and the material that is supplied is not in accordance with specifications? Does the answer to this question change when the supplier specifically states that the contractor is to test the material before it is supplied and, if it fails to do so, can make no claim regarding the quality of the material? These questions were answered in Earthco Soil Mixtures Inc. v. Pine Valley Enterprises Inc., a 2024 decision of the Supreme Court of Canada.
Factual Background
The City of Toronto hired a contractor to remediate the effects of basement flooding in a residential area. The remediation including the removal and replacement of existing topsoil with another topsoil better suited to water drainage. The prime contract initially called for a substantial performance date of August 19, which was ultimately extended to October 15. Liquidated damages applied for every working day thereafter.
Continue Reading >Joinder
The simple question for this newsletter is whether a statement of claim to enforce a claim for lien can also join a trust claim to that lien claim. This issue was dealt with in Devlan Construction Ltd. v. SRK Woodworking Inc., a 2023 decision of the Divisional Court. The answer to the question was dependent on statutory interpretation, an esoteric exercise that lawyers and judges often must perform, but which we normally spare our readers. But not this time. We are going to give you the reasoning behind a relatively simple answer to a simple question – if only so that you understand the intellectual exercises in which lawyers and judges must sometimes engage for a case.
Continue Reading >Registration Complete
Gay Company Limited v. 962332 Ontario Inc. 2023 Ont SCJ
Under the Land Registry Reform Act and the Land Titles Act the registration of an instrument is complete only when the registrar certifies it. Once certified, the instrument takes its date and time from when it was originally submitted for registration. Until an instrument is certified, the party requesting its registration may withdraw it. Accordingly, in this case when a discharge of lien was registered in error, the registering party had the right to withdraw it before certification.
Continue Reading >Adjudication Effects
Adjudication is the means by which the prompt payment provisions of the Construction Act (“Act“) are enforced. An adjudication decision will order, on an interim basis, that a party either pay or not pay money to another. It is interim because an adjudication order can be overturned in an arbitration or court proceedings. Does an adjudication decision have any other effect on the parties? This question was answered in Arad Incorporated v. Rejali, a 2023 decision of the Ontario Superior Court of Justice.
Convoluted
This case demonstrates the usual problems with a residential project. No one really knew who was contracting with whom. We have a corporate plaintiff (call it the subcontractor) and the subcontractor’s principal. We have a general contractor. And we have two owners.
Continue Reading >Costs (2)
Speaking of costs, in Prasher Steel Ltd. v. BWK, a 2023 decision of the Ontario Superior Court of Justice, the defendants were wholly successful in a decades-long contract dispute. The trial judge was tasked with determining the appropriate scale, and award, of costs.
The defendants asked for substantial indemnity costs. The judge noted that the normal scale of costs is only partial indemnity and that a higher scale of costs is reserved for exceptional circumstances, such as reprehensible or outrageous conduct on the part of one of the parties. Here, the judge agreed that substantial indemnity costs were appropriate for several reasons:
Continue Reading >Lien Start Date
When a subcontractor supplies materials or services (collectively, “services“) to an improvement and is not paid, it has the right to register a lien against the project lands. Under the current Construction Act, a sub has to register its lien within 60 days of the last supply of the services. Under the old Construction Lien Act, a sub had only 45 days. The lien period also starts to run upon publication of substantial performance of the prime contract, but that alternative is not the subject of this newsletter. So, when does the sub last supply its services? That was discussed in Ozz Electric Inc. v. Bondfield Construction Company Limited, a 2023 decision of an associate judge of the Ontario Superior Court of Justice.
Parties
The sub, Honeywell, supplied services; the general, Bondfield, did not pay for them in full; and Honeywell registered a lien against the project lands on February 21, 2020. This registration was based on an alleged last supply of services of January 8, 2020. The project was governed by the old Construction Lien Act so that Honeywell had only 45 days to register its lien.
Continue Reading >Costs Against Non-party & Increased Costs
Prasher Steel v. BWK Construction Company 2023 Ont SCJ
The general was wholly successful against the sub. The general tried to get costs awarded against the sub’s principal, but was unsuccessful because the principal had done nothing improper during the proceedings and had not acted fraudulently or deceitfully. The judge did award substantial indemnity costs against the sub; the general had beaten its offer to settle and the sub’s lien was excessive.
Continue Reading >Unlienable Items
Chesney v. Malamis 2023 Ont SCJ
Contractor liened for the amount specified in his invoice. It was apparent that all but $15,000 of the invoice had nothing to do with actual work being valued; it was, in essence, a claim for an equitable interest in the property being renovated. The judge noted that the damages such as loss of profits, lost opportunity costs, property management fees, and head office overhead were not improvements and were not lienable. The judge reduced the security from $173,000 to $15,000.
Continue Reading >Adjudication and Payment into Court
Arad Incorporated v. Rejali 2023 Ont SCJ
Contractor liened for money owed. In the meantime, the parties had two adjudications: one by the contractor for money owed and the other by the owner for money overpaid to someone associated with the contractor. We gather that the adjudicator had little evidence to go on and ultimately dismissed both adjudications. He held that the contractor had been paid everything to which it was entitled and that any overpayment was made to someone other than the contractor. The owner, who had paid money into court to vacate the contractor’s claim for lien moved for the return of that money. The judge refused. He held that an adjudicator’s decision was an interim decision and that it did not bind the court; it was merely one piece of evidence. The adjudicator’s decision alone was therefore insufficient to justify the loss of the contractor’s security.
Continue Reading >