Call us: (905) 366 9700

Legal Blog

Contract Interpretation

Posted on August 24, 2026 | Posted in Construction, Five Liners

Brillion Homes Ltd. v. Tony Hayre Management Services Ltd., 2026 BCCA 303

A construction manager claimed against the owner after a project was delayed and invoices remained unpaid. The contract was for a 12-month completion and valued at $220,000, payable at $15,000 per month. The project was delayed for three months and the construction manager stayed for two of those three months and claimed an extra $30,000 for its time. The trial judge held that there was an implied term that the owner was to pay the manager $15,000 per month. The Court of Appeal held that it was not open to the trial judge to imply a term that contradicted the contract, which had a fixed sum of $220,000. The Court of Appeal therefore held that the total amount to which the manager was entitled was $220,000 x 14/54 = $205,333.

 

Jonathan Speigel

 

Written by Jonathan Speigel, the founding partner of Speigel Nichols Fox LLP, leads the litigation and construction practices.

Share:

Download our free checklist:

“10 Questions to ask before hiring a law firm”

DOWNLOAD

Speigel Nichols Fox LLP