2283624 Ontario Limited v. Performance Heating & Floor Coating Ltd. 2017 Ont SCJ

The judge awarded costs of $45,000 to the defendant on an unsuccessful construction lien action for payment of $59,000. He dismissed arguments of proportionality because, he stated, it was the plaintiff who made the decision to use the Construction Lien Act process rather than sue in Small Claims Court or use the Simplified Rules.

 