Fixed Price Contract

Posted on March 15, 2021 | Posted in Construction, Five Liners

1157391 Ontario Inc. v. Ortiz 2020 Ont SCJ

Defendant owner wanted contractor to justify costs on a fixed price contract payable in stages of construction. The judge held this was unnecessary. The defendants had no right to convert a fixed price contract into a labour and material contract by their wishful thinking.

 