Legal Blog
Tender Reversal #2
In our newsletters of July 2004 and September 2004, we dealt with the Superior Court of Justice decision in Toronto Transit Commission v. Gottardo Construction Ltd. It would be fair to say that we were not overly impressed with the reasoning behind the decision. The owner appealed that decision and the Ontario Court of Appeal has now rendered its judgment.
Trial Decision
The general submitted a tender in response to a call for tenders. The general made a $1.1 million mistake in its tender, which was apparent to it but not to the owner. The tender called for the general to submit a breakdown of its contract price after submission of the tender and to submit further documents. The general submitted a breakdown of a higher amount with the error corrected, but did not submit the required documents.
The trial judge held that the breakdown demonstrated an error on the record that resulted in the owner being unable to accept the tender. The trial judge also held that the failure to submit the required documents rendered the tender non-compliant and therefore incapable of acceptance. Finally, the trial judge held that even if there had been a valid contract A, she would have rescinded the contract because it would have been unjust to have enforced it.
In our September 2004 newsletter, we said:
“If either reason for the dismissal withstands appeal, the owner is put in a dilemma. If it asks for further clarification of the bid, the general can demonstrate that there is a mistake on the face of the tender and be released from the tender. If it asks for further documents, then it puts the general in a position in which, by refusing to do what it is supposed to do, the general can withdraw its tender. We do not usually have a whole lot of sympathy for owners, but these results do not seem to make much sense.”
“Her decision turns Ron Engineering on its ear. The argument that the judge accepted in this case could have applied equally well in Ron Engineering. … The use of the rescission remedy opens the floodgates for arguments that can nullify the law of tender, law that has been accepted for the past 23 years.”
Issues: Error on Face and Non-Compliance
The Court of Appeal noted that “the trial judge appears to have confused the creation of Contract A and the process of analysis that leads to the acceptance of the tender and the formation of Contract B.” Contract A is not formed after the general submits the breakdown and the required documents; Contract A is formed the moment that the owner opens the general’s tender. The terms of contract A are set out in the call for tenders. In the TTC case, one of those terms called for the submission of a proper breakdown of values aggregating to the actual bid, not the bid that the general wished that it had submitted. Another term required the proper submission of the specified documents.
The Court therefore held that the general’s submission of an erroneous breakdown of values did not demonstrate that the original tender was incorrect on its face; rather, the improper submission was, in itself, a breach of contract A by the general. Similarly, the failure to supply required documents did not render the tender non-compliant; the tender was already compliant. The failure to supply was a breach of contract A.
Accordingly, contract A was valid and the general breached it by its failure to adhere to the terms contained in it.
Issue: Rescission
The Court of Appeal noted, “rescission may only be granted in cases of unilateral mistake when the unmistaken party engaged in fraud or some other unconscionable conduct or where the unmistaken party contributed to the mistake.” The Court noted that the trial judge found that the owner did not contribute to the general’s mistake and that there was no fraud on anyone’s part. Accordingly, the actions of the owner had to be unconscionable for the agreement not to be enforced.
The Court held that there were no unique circumstances in this case to distinguish it from Ron Engineering. Although there would be financial hardship on the general, that would be insufficient to warrant rescission. The Court felt that the burden imposed on the general was not so grossly disproportionate to make the enforcement of the contract unconscionable.
Result
The Court allowed judgment in favour of the owner for $434,000, the difference between the general’s bid and the next high tenderer. The Court also granted judgment for interest, costs of the appeal of $35,000, and costs of the trial.
As it happened, it made economic sense for the general to refuse to enter into contract B because to do so would have cost it $1.1 million, rather than $434,000. The real mistake of the general was not paying up. We would guess that that decision cost it another $200,000-$300,000 in its own legal fees and those that it will have to pay to the owner.